Abstract
Production planning with lot-sizing and scheduling in industries where the cleaning times
depend on the sequence of the products can be modelled as a mixed integer problem. However,
this problem is very hard, and even small instances cannot be solved exactly in a reasonable
time. We propose a division of the whole production planning problem into its two subproblems,
and to solve each them independently: first the lot-sizing, then schedule the operations that
were determined for each machine, for each period. In this strategy, the lot-sizing part does not
take into consideration the changeover times. After scheduling the operations, if the cleaning
times make a solution infeasible, a constraint cutting this solution must be added. The lot-sizing
problem must be resolved, and its solution rescheduled, until obtaining feasibility. We propose
an algorithm for integrating lot-sizing and scheduling, and analyse the results obtained.
|